GROUP: |
Building |
TYPE: |
Bldg-Alter/Repair |
SUB-TYPE: |
Commercial |
PRIMARY USE: |
(13) Office |
WORK DESCRIPTION: |
INTERIOR TENANT IMPROVEMENT ON FLOOR 08 IN EXISTING EIGHT STORY BUILDING.
|
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
08/12/2023 |
ISSUING OFFICE: |
CURRENT STATUS: |
Issued |
CURRENT STATUS DATE: |
08/12/2023 |
|
|
Submitted |
04/18/2023 |
APPLICANT |
Assigned to Plan Check Engineer |
04/22/2023 |
HERNAN ARREOLA |
Corrections Issued |
05/02/2023 |
HERNAN ARREOLA |
Quality Review Completed |
05/04/2023 |
TEODORO DIAZ RODRIGUEZ |
Plan Check Approved |
08/11/2023 |
HERNAN ARREOLA |
Issued |
08/12/2023 |
APPLICANT |
Redevelopment Project Area |
Cleared |
05/10/2023 |
DAVID URITA |
Green Code |
Cleared |
06/14/2023 |
MICHAEL AYERS |
DAS Clearance |
Cleared |
07/26/2023 |
HERNAN ARREOLA |
|